Your open job value,
against your own limit.

List the jobs you have under way and enter the Open Job Value limit from your own certificate. The calculator adds up the contract value of every job that is not yet complete, shows your headroom against the limit, and how much more contract value fits under it. It follows the NSW HBCF method; other states differ.

Written by Brad Caldon, Founder, VIABUILD. Licensed builder (NSW) · Registered Building Practitioner (Class 1 to 9) · B.Construction Management (Hons) · Last reviewed 28 September 2026

01 / The calculator

Work it out

A contract value per job and your limit to start. Progress on each job and your job number limit are optional, and each adds a line to the result.

Your current jobs

100% takes the job off the list. Blank counts it as open.

100% takes the job off the list. Blank counts it as open.

Your limits

The figure on your own certificate of eligibility or from your insurer. Nothing is filled in for you.

The maximum number of incomplete jobs, if your certificate states one. A whole number.

Open job position

Enter the contract value of each job you have under way, and the Open Job Value limit from your own certificate. Progress and the job number limit are optional, and each one adds a line below.

02 / The method

How open job value is calculated

In NSW, a builder needs a certificate of eligibility from the Home Building Compensation Fund before buying certificates of insurance for residential jobs. The certificate records the builder's Open Job Limits, which come in two parts:

  • Open Job Value (OJV). The maximum total contract value of incomplete jobs the builder may have at any one time.
  • Open Job Number (OJN). The maximum number of incomplete jobs. Builders cannot exceed their approved number.

The calculator applies that definition and nothing more:

  • Open job value is the sum of the contract values of every job that is not complete. A job counts at its full contract value, however far along it is.
  • Headroom is your limit less the open job value. When the open job value is above the limit, the calculator shows how far over it you are instead.
  • More contract value you could take on is the headroom, never less than zero. It holds until a job on the list completes and drops out.

Progress is used for one thing: telling whether a job is still open. Enter it as a percentage complete or as the value of work remaining, whichever you track. A job at 100%, or with $0 remaining, drops out of the total. A job with no progress entered counts as open. The work still to build is shown as a separate line for reference, because it is the figure builders most often mistake for their open job value.

Two things the method leaves to you. When a job stops counting as incomplete for your certificate is not something this page can settle, so you decide when to mark it complete, and your insurer can confirm the point. And whether contract value should include GST and approved variations is not settled in our sources either, so enter every job on the same basis and check it with your insurer. Why the limit exists and what sets it are covered in the Open Job Value guide, and how the NSW assessment works in the NSW HBCF eligibility guide.

03 / Worked example

Four jobs and one limit

An example only. The figures are made-up round numbers chosen to show the arithmetic, not a typical limit or a typical job. Say the limit on the certificate is $2,000,000 and the builder has four jobs:

  • Job A: contract value $600,000, 40% complete. Open, counts $600,000.
  • Job B: contract value $500,000, 100% complete. Drops out, counts $0.
  • Job C: contract value $400,000, $300,000 of work remaining. Open, counts $400,000.
  • Job D: contract value $700,000, not started, no progress entered. Open, counts $700,000.

Open job value is $600,000 + $400,000 + $700,000 = $1,700,000. Headroom against the $2,000,000 limit is $300,000, so the builder could take on $300,000 more contract value before a job completes.

Now the mistake. Adding up the work still to build instead gives $360,000 + $300,000 + $700,000 = $1,360,000, which looks like $640,000 of headroom. A builder who tendered on that number would be $340,000 over the limit if they won. That gap is why the calculator keeps the two figures apart.

04 / Near your limit

If the headroom is thin

  • Check both limits. Value headroom does not help if the number of incomplete jobs is already at your Open Job Number. Enter it in the optional field.
  • Headroom comes back when a job completes, not as it progresses. Under the definition above, a job keeps its full contract value on the list until it is complete, so the date a job finishes matters more than how fast it moves.
  • Watch jobs that grow. A contract variation of more than 20% of the original price, up or down, has to be notified and triggers an additional premium or a refund.
  • The limit follows the financial position. The NSW assessment tests financial capacity using Adjusted Net Tangible Assets (ANTA), measured against a turnover worked out as if your Open Job Limits were fully used over a year, and each OJV band needs a minimum eligibility score. The eligibility manual provides for a Builder Profile Change to meet the minimum ANTA for a higher OJV. How the financial position is built and presented is the subject of the Open Job Value guide.
  • Check what you can fund, not only what you are allowed. Working capital is often the lower ceiling, and it binds first. The funding the work you win guide covers it.
  • Eligibility is not permanent. icare may revise, suspend or cancel a builder's eligibility at any time, so confirm the current figure with your insurer before you rely on it.

05 / Before you rely on it

An estimate, not advice

This calculator gives an estimate from the figures you enter. It is general information, not insurance, legal or financial advice, and it does not tell you whether you are eligible for cover or can take on a particular job. It follows the NSW HBCF definition as recorded from the Eligibility Manual (version 12, effective 2 March 2026); the scheme's rules and figures change between versions, and other states' schemes work differently. Your certificate of eligibility and your insurer are the authority on your limit and on what counts toward it. Nothing you type leaves the page.

06 / FAQ

Common questions.

Under the NSW Home Building Compensation Fund, Open Job Value is the total contract value of the builder’s incomplete jobs at any one time. So the sum is simple: list every job that is not yet complete and add up the contract value of each one. The number that matters is that total against the Open Job Value limit recorded on your certificate of eligibility. The calculator above does exactly that, and shows the gap between the two as headroom.

Not under the NSW definition. Open Job Value is measured on contract value, not on the value of work still to do, so a job that is 90% built counts at its full contract value until it is complete. That is the most common way to misread your own position. The calculator shows the work still to build as a separate line for reference, and keeps it out of the open job value for that reason.

On your certificate of eligibility. In NSW, a builder needs a certificate of eligibility before buying certificates of insurance, and the certificate records the builder’s Open Job Limits: the Open Job Value and the Open Job Number. If you are not sure of the current figure, ask your insurer. The calculator never fills one in for you, because a limit the builder did not supply would be a limit someone invented.

The other half of the Open Job Limits. Where Open Job Value caps the total contract value of incomplete jobs, Open Job Number caps how many incomplete jobs you can have, and builders cannot exceed their approved number. Both limits apply at once, so a builder with value headroom can still be unable to start another job. Enter your job number limit in the optional field and the calculator shows how many more jobs fit under it.

The arithmetic is the NSW HBCF method and nothing else. Other states run their own home warranty schemes, Domestic Building Insurance in Victoria and the Home Warranty Scheme in Queensland among them, and their mechanics and thresholds differ. If you build outside NSW, confirm how your own scheme measures the work you have open before relying on this number. The state-by-state home warranty guide is the place to start.

Our source material does not settle that, so this page does not guess. The calculator adds up whatever figures you enter. Enter every job on the same basis, and confirm with your insurer how your certificate measures contract value. Separately, in NSW a contract variation of more than 20% of the original price, up or down, has to be notified and triggers an additional premium or a refund, which is worth knowing when a job is growing.

07 / Keep reading

The references behind this calculator

The guides that explain where the limit comes from and how to lift it, the knowledge nodes on warranty insurance and financial capacity, and a companion calculator.

08 / Cite this

How to cite this page

To reference this page, use the wording below and link the page rather than copying it, so readers reach the current version. Corrections to hello@viabuild.au.

Citation

Brad Caldon, VIABUILD, Open job value calculator, https://www.viabuild.au/tools/open-job-value-calculator, last reviewed 28 September 2026.

Know your open work before the next tender.

The limit is read off the books, so the books need to be right. VIABUILD connects to Xero, which stays your accounting system. The estimate becomes the job budget, and purchase orders are raised from its lines.